Kepler LT conference call =================== Aug 10, 2011 Participants: Jones, Ludaescher, Schildhauer, McPhillips, Altintas, Brooks Agenda and Notes: --------------------------- * K/C final report (end of August), due 90 days after (end of November) -- Bertram: will organize and compile report overall -- All: send pubs -- Ilkay: survey of projects using Kepler; also individual users, especially PhD students -- use form on plone site -- Ilkay: should compile scientific pubs arising from Kepler -- Matt: compile download stats over time * Dependency problems with build/module system * Ilkay's items -- release plans -- Derik working on Kepler 2.3 release, and reporting modules release -- Need to plan 2.4 release -- Ilkay: should plan on including 'redirect; code in 2.4 -- Include sensor-view support -- Ilkay: theme to bring other communities in -- how do we manage the release process? coordinate via the release roadmap pages for each release -- note that the release page dates are out of date -- update this: https://kepler-project.org/developers/teams/build/kepler-release-roadmap -- how do we decide which bugs get fixed in the releases? -- especially considering the lack of funding? -- release manager: good, but also need a mini release team -- Tim: release team should control when a release is ready -- Tim: part of the problem is that our developers are not users, so don't always have the same perspective as users -- more outdated stuff on the web page: https://kepler-project.org/developers/management (Bertram, Mark: K/LT terms expired) -- broken links: ---- https://kepler-project.org/developers/teams/build: Build and Release Team Charter (https://code.kepler-project.org/code/kepler-docs/trunk/teams-and-wg/2-teams/build-release/kepler-build-release-charter.doc) * Support issues -- need to do a better job supporting users as requests come in -- assignments were working reasonably, but we need to stay organized -- bug handler/triage: -- @NCEAS: Matt, Derik, Jing -- @Ptolemy: Christopher -- @Davis: Lei, Sean -- @UCSD: Ilkay, Dan, Jianwu -- rather than having individuals sign up, instead have groups sign up each week -- triage person to identify what is really wrong, follow through to completion -- reminder person: Matt * Funding projects update -- UC Davis: FilteredPush project with Harvard University uses Kepler for "curation workflows" (1 FTE: postdoc) -- USCSB/Cornell: Science Pipes for Education with ESA (~ 0.75 FTE engineer for 14 months) -- working with a bunch of scientists to build educational workflows for science classes -- UCSD: bioKepler/NSF ABI (1.5 FTE through end of 2014) -- UCSD: DISCOSci/NSF CDI (0.5 FTE through end of 2103) -- UCSD: CAMERA/Moore F. (0.5 FTE through end of 2012) Issues to roll over to next conf call: * Future funding * newsletter * outreach * Bertram, Mark: K/LT terms expired